STANDARD
  • DESCRIPTION OF WORK

 

FOUNDATION AND BASEMENT:- 

Earth work excavation 4’0” x 4’0” x5’0” (upto Hard Surface) PCC & Sand filling 4” tk

Bed concrete 9” tk. Tapper Concrete 1’(Isolated footing)

Footing mate 10mm dia in both ways 150mm c/c.

Plinth beam 2/3nos 12mm dia & bottom 2/3nos 12 mm dia @ top. (as Per Structural Drawings)

REINFORCEMENT CEMENT CONCRETE:- (as Per Structural Drawings)

Column size 1’-0” x 0’-9” & 0’-9” x 0’-9” (R.C.C. 1:1½:3 concrete)

Steel size, 12mm -4/6nos with 8mm rings @ 7” c/c

Lintel (2nos 10mm dia & bottom 2nos 10mm dia @ top 8mm dia stirrups @ 6” c/c R.C.C concrete

1:1½:3

Roof beam (3nos 12mm dia @ bottom 3nos 12mm dia @ top 8mm dia stirrups @ 7” c/c Roof slab 10mm main rod & 8mm distributor @ 6” c/c (R.C.C. concrete 1:1½:3, 0’ – 5” tk)

BRICK WORK:-

Basement wall brick work 9” tk using Flyash Bricks above plinth beam to basement level to 2’6”

height.

Brick work wall in c.m. 1:6 using chamber bricks walls thickness 0’- 9” & 0’ – 4.5” tk height 9’-6”

for each floor

PLASTERING WORK:-

Ceiling plastering with c.m 1:3 Inner Wall plastering with c.m 1:4 Out wall plastering with c.m 1:4

WALL CUPBOARD:-

Bed room cupboard – 1no (size 7’ 0” height, 4’-0” breadth, 1’-6” depth, side wall in bricks &

caddappa slab) & Laft Single Side Each BedRoom & Kitchen.


DOORS, WINDOW & VENTILATOR:-

Main door- Teak Wood Door and Frame

Bedroom - Designer Readymade Doors with Teakwood Frame. Windows - UPVC Windows with MS Grill.

Bathroom Door – Syntex PVC (Heavy)

 

PARAPET WALL:-

For the proposed construction wall around parapet wall 0’-9” tk pillar 0’-4.5” tk partition, wall height 2’6” & both side plastering.


PAINTING WORK:-

Ceiling one coat Birla Whitecem and Two coat Emulsion White Wall inside two coat Putty, One coat primer & Two Coat Color Paint Outside one coat Birla Whitecem & two coat Exterior paint


PLUMBING WORK:-

Supplying & fixing of CPVC ¼” & ¾” (Inside toilets)

I.W.C White closet & E.W.C White Closet

Tank delivery to bath room, Kitchen, 1” P.V.C. Pipe open type

Drainage line 4” P.V.C. Pipe 4 gauge, Waste line 2 ½” P.V.C. Pipe 4 gauge Inspection Chamber 2’0” x 2’0” 1 no with R.C.C. slab cover

Rain water pipe 4” P.V.C. Pipe 4 gauge Kitchen SS Sink 24”x18”


FLOORING TILES:-

Flooring tiles 2’-0” x 2’-0” as per our tiles rate per sq.ft 50/-

Wall tiles 0’-12” x 0’-15” as per our tiles rate per sq.ft 40/- Bath room wall tiles height 7’0” Kitchen top with Granite Platform & wall tiles 0’-12” x 0’-18” tiles height 2’-0”

Bath room tiles flooring 0’-10” x 0’-10” as per tiles rate per sq.ft 40/-



FOLLOWING MATERIALS ARE USED FOR CONSTRUCTION:

 

 

S.No

 

Material

 

Brand

1

 


2

 

3

 

4

 

 

5

 

6

 

Cement Steel



Outer Paint

 

Inner Paint & Putty

 

 Sanitary Fittings 



Electrical


Bricks Sand

Dalmia / Chettinad / Ramco GBR – Fe 500 Grade


Asian Exterior Paint

 

MYK Laticrete / Birla / Asian Putty & Asian Tractor Shyne Emulsion Paint

 

Parry ware or Equivalent

 


Finolex or Orbit ( FR ) wires, Roma/ Legrand Switches

Chamber Bricks & Flyash Bricks(Basement only) Polished M- Sand & P Sand

 

  • THE FOLLOWING WORKS ARE NOT INCLUDED IN OUR QUOTATION:

 

  • BUILDING PLAN APPROVAL
  • M.E.S. LINE CONNECTION (SINGLE OR THREE PHASE)
  • BORE WELL & MOTOR
  • OVER HEAD TANK (BRICK WORK)
  • ELECTRICAL FITTING (FAN, TUBELIGHT, EXHAUST FAN, ETC)
  • SUMP & SEPTIC TANK
  • COMPOUND WALL
  • ELEVATION CLADDING WORKS